The Sindh Regulation of Electric Power Services Act, 2023
The parent statute. Establishes the Authority, confers the licensing, tariff, market and enforcement powers, and fixes the boundary with the federal framework.
The Sindh Regulation of Electric Power Services Act, 2023 and the instruments being made under it. The instruments below are in draft and will be published for consultation.
The parent statute. Establishes the Authority, confers the licensing, tariff, market and enforcement powers, and fixes the boundary with the federal framework.
Regulations for the grant, amendment, renewal, suspension and cancellation of a microgrid licence under section 18 of the Act. A single unified licence authorises generation, distribution and supply within an unserved or underserved territory, within the notified voltage and capacity limits.
All five licence types, captive registration and concurrence. Jurisdictional screening, application procedure, criteria, modification, renewal, suspension and cancellation.
Who may contract, price freedom with filing, confidentiality of commercial terms, open access, use of system charges and the grounds on which a contract may be reopened.
Every fee separately defined and levied by its own regulation. One table of fees in seven parts, due dates, indexation and the matters on which no fee is payable.
How the Authority makes rules: the consultation period, the treatment of submissions, and the statement of reasons published with every instrument.
When a tariff falls to be determined, the petition, notice, public hearing and the reasoned determination. Does not apply to a price agreed in a bilateral contract.
When a hearing is required, notice, intervention, evidence, confidentiality, interim orders and reasoned decisions.
How a consumer complaint is received and decided, free of charge, and how the Authority inquires into a contravention of its own motion.
The scale of fines, the matters in aggravation and mitigation, and the procedure before a fine is imposed.
Mediation, expert determination for technical questions, and arbitration. Awards enforceable as decrees. Seat at Karachi.
The right to seek a review of a decision of the Authority, the period within which it must be sought, and how a review is decided.
Regulations governing the meetings, conduct of business, decision-making, minutes and records of the Authority, including committees, wings, associations and related procedures.
The basis on which wheeling charges are computed and filed, with the impact statement and the comment form.
The sanctioned load at a single premises at or above which a consumer may buy under a bilateral contract at a price the parties agree.
The limits within which a unified microgrid licence may be granted, and the position above them.
The vocabulary in which a geographic, spatial or virtual service territory is to be described in an application and in a licence.
Forms A-1 to A-12, undertakings U-1 to U-8, instruments C-1 to C-5, the standard licence L-1, the annual return R-1 and the fee forms F-1 to F-3.
The published period for each step from receipt to issuance. Nothing is granted by lapse of time.
Planning, connection, operation and maintenance of a distribution system within the Authority's domain.
Meter classes, accuracy, sealing, testing intervals and the resolution of a metering dispute.
Connection, billing, disconnection and reconnection, and the standards a consumer may expect.
Standards of supply quality and reliability, protection and earthing, safety clearances and reporting.
Do you need a licence; eligibility and minimum solvency; term of a licence; section 13 and captive use; how an application is processed; fees at a glance.
How the Authority identifies a matter falling within federal competence, and what happens to an application which touches it.
Every determination is published in full within seven days of the decision, alongside the instrument to which it relates.
Everything above except the Act is in draft and coming soon. Each will be published for comment before it is made. If you are planning a project and want to know where matters stand, the facilitation desk will tell you, free of charge.
The Authority regulates electric power services within the Province for which a licence or registration is required under the Act.
Every application is screened before it is registered. Where any part of the proposed activity falls, or may fall, within the regulatory competence of the Federation or of an authority established under Federal law, the Authority does not proceed upon it.
The application is returned with written reasons and the fee is refunded. It is not severed, and no part of it is processed.
Is any part of the plant connected, directly or indirectly, to the national grid, including a standby connection? If it is, the project falls outside the provincial framework and the federal framework governs. Declare it early and nobody wastes time.